Krångede kraftverk

Krångede kraftverk

Architect

Erik Hahr

Year

1931

Type

power plant

At Krångede on the Indalsälven the machine hall sits blasted out 40 meters below ground, and that governs how the plant looks above ground. Erik Hahr had to express the idea of the works without a visible turbine hall, so he gave the…

Report an error

Something wrong on this page? Tell us what.

Loading map…
Directions

Photos

Krångede kraftverk
Krångede kraftverk
Krångede kraftverk
Krångede kraftverk

Timeline

  1. 1931

    Original construction

    Erik Hahr

  2. 1933-1936

    Completion

    Work on the dam began in the autumn of 1933 and was carried out during the low-water periods, with two openings twenty metres wide left between the dam piers so the river could keep running. They were closed for good over the winter of…

  3. 1936

    Completion

    Rock blasting for the machine hall was finished in the autumn of 1934 and the first generating unit was tested in April 1936. The first stage was inaugurated on 18 July by crown prince Gustaf Adolf and crown princess Louise before some 1…

  4. 1947

    Addition

    Construction continued in stages until six generating units were in operation, at that point the most powerful turbines and generators in the country. The plant reached its full built extent with this stage, fourteen years after work on…

More like this

Selections Krångede kraftverk belongs to

More in Hammarstrand

SaveI've been here

Read on, for free

Sign in to read the full text, see every photo, and save places.

By continuing, you agree to the Terms of Service and Privacy Policy.

Get the app

Get the app

Download on the App StoreGet it on Google Play